How to Replace a Load-Bearing Wall with a Support Beam for an Open-Concept Space
Determining Load-Bearing Walls
Before removing any wall, it’s crucial to determine if it’s load-bearing. Load-bearing walls support the weight of the floor above, so removing them requires installing a support beam to carry the load.
Step-by-Step Guide to Replacing a Load-Bearing Wall
Materials:
- Load-bearing support beam
 - King studs (2)
 - Jack studs (4)
 - Temporary steel columns (optional)
 - 2×4 dimensional lumber
 - 3 1/2-inch 16d galvanized nails or utility screws
 - 16-gauge galvanized metal hurricane straps
 - Sheet plastic or ZipWall dust barrier
 
Tools:
- Miter saw or circular saw
 - Framing hammer
 - Tape measure
 - Laser measurer
 - Adjustable steel columns (optional)
 - Sledgehammer
 - Eye protection
 - Hearing protection
 - Reciprocating saw
 - Pry bar
 - Carpenter’s pencil
 - Speed Square
 - 6-foot ladder
 - Car jack (optional)
 
Instructions:
1. Create a Support System:
- Use adjustable steel columns or 2×4 studs cut to length to support the ceiling while you remove the wall and install the beam.
 - Ensure the supports are placed under ceiling joists and against the floor.
 
2. Demolish the Existing Wall:
- Protect against dust by stapling plastic or using a ZipWall.
 - Use a sledgehammer or reciprocating saw to carefully remove the drywall and studs.
 - Cut out the horizontal ceiling and floor plates with a reciprocating saw and pry them away.
 
3. Install the King Studs:
- King studs serve as the backing for the beam’s ends.
 - Measure and cut a full-length stud for each end, and nail them into place between the floor and ceiling plates.
 
4. Attach a Temporary Beam Ledger:
- Create temporary ledgers by nailing short 2x4s or 2x6s to the king studs, less than an inch below the ceiling’s final contact point.
 - These ledgers will hold the beam in position while the jack studs are installed.
 
5. Cut the Support Beam:
- Measure the distance between the king studs and cut the beam to fit.
 - Use a power miter saw, circular saw, or hand saw, ensuring the cut is perpendicular to the beam’s face.
 
6. Position the Support Beam:
- Lift the beam into place and rest it on the beam ledgers.
 - Secure it temporarily to prevent shifting.
 
7. Use a Laser Measurer to Check Joist Movement:
- Monitor the distance between the ceiling and floor using a laser measurer to detect any sagging.
 
8. Create Side Cleats for the Support Beam:
- Attach 2×4 side cleats to the king studs at both ends of the beam to prevent it from slipping off the ledgers.
 
9. Lift the Beam into Place:
- Lift the beam firmly against the ceiling and block it in place at each end.
 
10. Fit the First Jack Stud:
- Measure and cut the first jack studs to fit tightly between the beam and the floor.
 - Rest the bottom end against the king stud and swing the top end towards the beam until it rubs slightly.
 
11. Set the First Jack Stud:
- Hammer the first jack stud into place and secure it with screws and nails.
 
12. Set the Second Jack Stud:
- Cut the second jack stud slightly longer and hammer it into place, ensuring it’s flush against the beam.
 
13. Raise the Jack Stud (if Necessary):
- If the second jack stud is too short, use a pry bar to raise it and align it flush with the beam.
 
14. Tie in the Support Beam:
- Toe-nail the beam to the ceiling joists and use hurricane straps to connect it to the jack studs.
 
15. Remove Temporary Support:
- Remove the temporary support wall and watch for any signs of stress in the beam or jack studs.
 
16. Remove Debris and Repair/Finish Surfaces:
- Dispose of construction debris and repair any drywall, trim, or flooring affected by the wall removal.
 
When to Call a Professional:
- Consider hiring a contractor if you’re not comfortable with the project, if it becomes unexpectedly complicated, or if structural issues arise.
 